The docket · PMF-HI-26-002 · Hawaiʻi · ACTIVE
Active official proceeding · PMF recommendation
Customer Battery and Flexible-Load Grid-Services Tariff
Implementation recommendations for the Public Utilities Commission’s virtual-power-plant proceeding: pay separately for measured availability and delivery, protect a customer outage reserve, make enrollments portable if an aggregator fails, and let any resource that passes a performance test compete.
April 22, 2026 – present · PUC Docket No. 2026-0084

Act 266 of 2025 requires the Public Utilities Commission to set a goal for new customer-sited energy resources installed by December 31, 2030, and to establish grid-services tariffs with “fair compensation.” Any such tariff must include a rider for new and existing storage, let aggregators enroll customers, receive dispatch signals, submit measurement data and be paid directly, and allow storage performance to be measured at the device without a second meter. On April 22, 2026, the Commission opened Docket No. 2026-0084 to design a virtual power plant program, with initial guidance favoring remote dispatch, performance-based compensation and access for low- and moderate-income households.
The resource is already on rooftops. Act 266’s findings report that 96 percent of residential rooftop solar installations in the State now include storage, and Hawaiian Electric counted 120,570 rooftop systems at the end of 2025. The Commission’s own finding is that many of these resources are not optimized to support grid reliability. Earlier programs show both the potential and the limits: Battery Bonus filled its 40-megawatt Oʻahu cap in December 2023; the Shift and Save time-of-use pilot closed to new enrollment on February 1, 2025, with about 14,000 customers; and the current Bring Your Own Device Plus offer pays $400 per committed kilowatt up front, plus export credits for a two-hour daily window, over a five-year commitment.
Contract design is where programs succeed or fail. When the aggregator Swell Energy closed in September 2024, Hawaiian Electric paused monthly credits to about 1,200 enrolled customers, unenrolled their systems and paid upfront incentives the company owed. No customer should again depend on a single private intermediary’s solvency to keep a grid-services contract whole.
PMF’s recommendation is that the tariff buy defined services rather than enrollment. Customer batteries and controllable loads can reduce the evening peak and respond in seconds; they cannot supply multi-day energy, black start or transmission support, and should not be paid as if they could. In an illustrative Airform feeder study for Kailua, a 16-megawatt, 27.4-megawatt-hour customer fleet covers 55 percent of a modeled shortfall caused by a 30-megawatt campus load — useful, partial, and dependent on the hours the grid actually needs.
The record
The record
Act 266 (SB 589 CD1), approved July 2, 2025, added HRS §269-A through §269-D. Section 269-A requires the PUC to set a 2030 installation goal for customer-sited resources and establish tariffs with a storage rider, aggregator participation and device-level verification. Section 269-B requires compensation values for “resiliency, capacity, and ancillary service value.” The Act sets no numeric target; the separate goal of 50,000 distributed installations by 2030 comes from Gov. Josh Green’s Executive Order 25-01 of January 29, 2025.
What is in force
Bring Your Own Device Plus pays $400 per committed kilowatt up front, with an equal adder for low- and moderate-income customers, for a customer-selected two-hour daily export window and a five-year commitment. Hawaiian Electric’s example: a 15 kWh battery commits 5 kW for two hours, earns $2,000 up front and averages about $52 a month in export credits. That works out to roughly 17 cents per exported kilowatt-hour, and about $1,025 per committed kilowatt over five years including the upfront payment.
What the earlier programs showed
Battery Bonus reached its 40 MW Oʻahu cap in December 2023; Act 266’s findings add 6 MW on Maui. Shift and Save, a one-year time-of-use pilot, closed to new enrollment on February 1, 2025, with about 14,000 customers. Swell Energy’s Home Battery Rewards program ended when the company closed in September 2024; Hawaiian Electric paid the upfront incentives owed to roughly 1,200 customers and paused monthly credits.
What the model shows
Airform’s grid model, re-run on this site, places an illustrative 30 MW campus load on a Kailua corridor. The modeled shortfall peaks at 13.3 MW and lasts about 6.5 hours; a 16 MW, 27.4 MWh customer fleet covers 55 percent of it. The model prices that fleet at about $950 per firm kilowatt against $5,205 for a modeled utility build. These are illustrative feeder-study results, not a Hawaiian Electric plan or a forecast.
What we propose
- 01Pay separately for (a) availability in dollars per kilowatt-month, (b) delivered energy in dollars per kilowatt-hour during called events, and (c) a locational adder only on feeders where the utility has published a specific capacity need.
- 02Protect a customer-selected outage reserve, defaulting to no less than 20 percent of usable battery capacity, that the program may not dispatch below without the customer’s opt-in; suspend export dispatch and hold batteries charged in areas under a hurricane warning or a Public Safety Power Shutoff watch.
- 03Require aggregators to post financial assurance — a bond, escrow or letter of credit — covering outstanding upfront incentives, and guarantee that customers revert to a utility-administered default enrollment within 30 days of an aggregator’s exit, with accrued payments preserved.
- 04Implement device-level measurement and verification as Act 266 §269-A(c)(3) requires, using a published baseline method, and publish monthly aggregate results by island: enrolled kW, events called, kW delivered and payments made.
- 05Make eligibility technology-neutral: any resource — battery, controllable water heater, air conditioner, thermal storage or other flexible load — qualifies for a service class once it passes that class’s published performance test.
- 06Reserve a defined share of program capacity and enablement funding for low- and moderate-income households and renters, with no-upfront-cost participation options that do not require trading away the outage reserve.
- 07Prohibit resale of customer device or interval data without separate, informed consent, and give customers free download of their own device data in a standard format.
- 08Offer terms of five to ten years that transfer with the home on sale, with a published early-exit formula and a complaint process at the PUC.
Who pays, who benefits
- Program payments are recovered from all ratepayers through the utility’s revenue requirement. They are a good purchase only if they cost less than the capacity or fuel they displace.
- For comparison, the PUC capped recovery for the 253 MW Waiau repowering at $847 million, about $3,350 per kilowatt before fuel, adding about $3.62 a month to a typical Oʻahu residential bill. BYOD Plus pays about $1,025 per committed kilowatt over five years for a two-hour evening service. The two buy different things; the comparison shows the order of magnitude, not equivalence.
- Participants — disproportionately owners of homes with solar and storage — receive the payments. Nonparticipants benefit only through avoided procurement and fuel costs, which the Commission should estimate and publish.
- Measurement, verification, communications and administration add cost; PMF has not seen a public estimate for Hawaiʻi.
- Aggregator failure risk falls on customers and the utility unless assurance is required. The Swell closure showed the cost is real.
Test the numbers
Objections
“Two-hour customer batteries are not firm capacity. An island grid with no interconnection needs multi-hour and multi-day reliability that a virtual power plant cannot promise.”
Correct, and the recommendation is written around it: pay only for services a resource can demonstrate, and do not credit batteries for black start, transmission or multi-day energy. The tariff complements utility-scale procurement — including the 350 MW of grid-forming resources the PUC approved seeking for Oʻahu in August 2026 — rather than replacing it.
“Paying owners of $15,000 batteries raises rates for renters and lower-income households who cannot buy one.”
The cost-shift risk is real. The tariff should pay at or below a published avoided-cost benchmark, reserve participation capacity and enablement funds for lower-income households and renters, and report who participates by income band and island.
“Customers will not want a utility or a third party controlling their emergency backup.”
That is why the outage reserve, storm and shutoff suspensions, and override rights belong in the tariff itself, not in marketing materials. A program that customers abandon after the first hurricane season delivers no capacity.
What to watch
- PUC Docket No. 2026-0084: the next procedural order, program-design proposals and any interim tariff.
- PUC Docket No. 2024-0258: Hawaiian Electric’s approved requests for proposals (Oʻahu: 350 MW grid-forming, 81 MW firm); project selection expected September 2027.
- The PUC’s 2030 installation goal under Act 266 §269-A(a), which the statute requires but does not quantify.
- Act 24 (2026): the $40 million annual aggregate cap on the state renewable energy tax credit begins in 2027; EO 26-02 preserves the credit for systems placed in service in 2026.
Sources
- Act 266, Session Laws of Hawaiʻi 2025 (SB 589 CD1), approved July 2, 2025
- Hawaiʻi PUC, “PUC Opens Docket on Virtual Power Plant Program and Invites Participation” (Docket No. 2026-0084), April 22, 2026
- Hawaiʻi PUC, Docket No. 2026-0084 technical conference notice (June 16, 2026)
- Hawaiian Electric, Bring Your Own Device Plus program page (accessed October 4, 2026)
- Hawaiian Electric, “Hawaiian Electric’s Battery Bonus program hits cap on Oahu,” December 13, 2023
- Hawaiian Electric, “Hawaiian Electric to close Shift and Save time-of-use rates program to new enrollments as of Feb. 1,” January 9, 2025
- Hawaiian Electric, “Hawaiian Electric will pay customers with battery systems upfront incentives owed by insolvent third-party provider,” September 26, 2024
- Hawaiian Electric, “Hawaiian Electric in 2025 achieves 37% renewable energy across five islands amid spike in electricity demand,” March 10, 2026
- Hawaiʻi PUC, “PUC Approves New Firm Generation to Address Oʻahu’s Critical Electric Reliability Needs” (Docket No. 2025-0211), March 23, 2026
- Airform open grid and building models (assumptions and sources); Airform makes heat-pump and battery equipment
Evidence and implementation
Implementation dossier: federated battery grid services
A customer-sited fleet should be procured as a measured service with protected household reserve energy—not credited as a generic substitute for every central-grid asset.
Evidence reviewed September 7, 2026
Procure the service that the grid actually needs
Evidence & PMF analysisProgram announcement · source context
The Hawaiʻi PUC’s VPP design proceeding is an active policy context, not a final tariff. Its opening material discusses remote dispatch, performance compensation, customer-sited batteries and flexible devices. Hawaiian Electric’s customer-resource reports also show a substantial enrolled base while warning that export-only analysis does not measure all behind-the-meter behavior.
Sources: Order 42488 — VPP design proceeding (Hawaiʻi PUC)2026 Annual CER Program Review, Table 4 (Hawaiian Electric)2025 Annual CER Program Goals, pp. 18–19 (Hawaiian Electric)
PMF recommendation
PMF recommendation: a Commission-supervised tariff or procurement should specify the service by island and feeder—availability window, required kW, duration, response time, local deliverability, outage reserve, and rebound limit—before selecting technology. A battery, heat-pump water heater, cooling control, electric vehicle, or efficiency measure may compete only for the service it can measure and contractually deliver.
Separate enrollment, installation, and performance risk
PMF recommendationEligibility should turn on verified equipment, safe installation, customer consent, communications, and the ability to maintain a customer-selected or protected outage reserve. A provider may aggregate eligible assets, but it should bear platform, installation, maintenance, cybersecurity, and under-performance risk. The utility or program administrator should pay distinct rates for verified availability and delivered service; customers should not become guarantors of an aggregator’s capacity promise.
Procurement should be open and technology-neutral. Bidders should state installed cost, expected dispatchable kW and kWh, degradation assumptions, reserve policy, warranty support, customer payment, local labor plan, and transition procedure if the platform fails. A standardized customer agreement should say who owns each device, what happens on sale or exit, whether a hardware provider may remove equipment, and which party pays to replace a failed communications or storage component.
Measure device output, site load, and customer impact separately
PMF recommendationA credible fleet record needs separate views of device power, usable energy, net site load, export where relevant, state of charge, dispatch receipt, override use, and post-event rebound. PMF recommends independent measurement and verification using interoperable telemetry, time-synchronized event records, and audit access. Public reporting should aggregate results by feeder without publishing a household’s load profile or location.
Customers should receive a dashboard that explains each dispatch, payment, protected reserve, communication fault, and data permission. They must retain plain-language storm, health, safety, and public-safety-shutoff override rights. No retail sale of device or usage data should be permitted without separate informed consent, and loss of connectivity should fail safely into the customer’s reserve setting rather than silently create a penalty.
Scale in stages and test the portfolio honestly
PMF recommendationPMF recommends a staged sequence: device and cybersecurity qualification; a feeder-limited pilot with published reserve and payment rules; independent validation through actual events; then competitive expansion only where delivered service, customer bill effects, and distribution value meet the pre-set threshold. Low- and moderate-income participation should include enablement support rather than require households to surrender emergency energy to get basic affordability help.
Before capacity is treated as an alternative to a central asset, planners should compare same-service portfolios under chronological weather, outage, communications, distribution, N-1, and multi-day low-renewable conditions. A federated fleet can reduce a defined peak, reserve, or feeder need. It does not create primary energy and should not be represented as a blanket replacement for generation, protection, transmission, black-start, or long-duration adequacy.
Duration changes what a battery fleet can deliver
An illustrative fleet constrained by AC power, available energy and a 4 MW feeder ceiling. This scenario is not an accredited capacity value or a reliability forecast.
| Duration | Power limit | Energy limit | Feeder limit | Scenario output |
|---|---|---|---|---|
| 1 h | 4.5 MW | 6.3 MW | 4 MW | 4 MW |
| 2 h | 4.5 MW | 3.15 MW | 4 MW | 3.15 MW |
| 4 h | 4.5 MW | 1.575 MW | 4 MW | 1.575 MW |
| 8 h | 4.5 MW | 0.7875 MW | 4 MW | 0.7875 MW |
Equation and assumptions
MW = min(N × 5 × a ÷ 1,000; N × 10 × (1 − r) × a ÷ (h × 1,000); 4).
N is enrolled homes; a is assumed event availability; r is customer reserve; h is event hours. Each home has 5 kW AC power and 10 kWh AC usable energy before reserve. Availability constrains both power and energy. There is no recharge during an event.
The initial scenario uses 1,000 homes, 30% reserve and 90% availability. The 4 MW feeder ceiling is illustrative. Availability is a simplifying assumption, not a measured confidence interval. Chronological adequacy, dispatch response, local network conditions and rebound require separate evaluation.
Source context · reviewed September 7, 2026
- Order 42488 — VPP design proceeding — Hawaiʻi PUC. Docket 2026-0084; proposed design questions are not an adopted tariff.
- 2025 Annual CER Program Goals, pp. 18–19 — Hawaiian Electric. Export-only analysis does not observe self-consumption.
Reporting

Grid · Hawaiʻi · October 2, 2026
The Evening PeakOʻahu’s 7 p.m. problem: the sun sets and oil carries the evening
Rooftop solar fills the middle of the day. When it fades, Oʻahu still turns to oil. What the utility is buying for the 2030s, what customer batteries can carry now, and what they…

Policy · Hawaiʻi · September 17, 2026
AnalysisHawaiʻi’s home batteries are installed. The aggregator seat is open.
The Public Utilities Commission is redesigning how the state pays customer batteries for evening service. The last company to sit between those batteries and the utility failed in…

Markets · Hawaiʻi · California · September 11, 2026
AnalysisWhat California’s energy fights can teach Hawaiʻi, and what they can’t
California has more than 21,000 megawatts of batteries and some of the country’s steepest rate increases. Its export tariff, wildfire bills and connection deadlines give Hawaiʻi a…